Constructed re-support system and level out the carport cover

Constructed a re-support system and level out the carport cover. Removed the gutter and removed a portion of the roof shingles. Cut back approximately 20-24 inches of the plywood sheathing and rafter tails. Installed new blocking, fascia, gutter, and re-installed the shingles. Dig out four holes and pour in concrete post pads. Installed new 4x4 posts on metal brackets and 4x6 headers. Removed temporary support.